1. PI alerts the accounting techs of intent to submit a proposal. (the earlier the better)

2. PI fills out the Clinical Sciences Proposal Checklist and submits it to the accounting techs. http://www.cvmbs.colostate.edu/clinsci/CLINSCI CHECKLIT.pdf

3. The accounting techs will enter the proposal into the CSU PASS* system. http://pass.research.colostate.edu

4. PI prepares the proposal
• The PI has the choice of either downloading the Proposal Budget Spreadsheet (PBS) including the Proposal/Project Approval (SP-1)** from PASS to assist with the budget preparation or your accounting tech can prepare this for you.
• If applicable, complete any additional Sponsored Programs Forms
(SP-12 Request For Split of Indirect Costs, SP1-B Proposal Budget for Non-Federal Sponsors,)
• If applicable, submit forms to the Regulatory Compliance Office,
(i.e. ACUC Form A-100)
• If applicable, complete any required Sponsor forms, (i.e. grants.gov application, NIH, USDA forms)

5. PI submits the electronic file(s) via email of the proposal budget and budget justification using the sponsor forms provided to the accounting techs. (At least 14 days prior to submission date per CVMBS SOP)

6. The accounting techs will review the proposal budget to ensure that the budget meets the sponsor’s requirements and fits within University guidelines. They will then route the proposal budget through the CVMBS Research Administrator and Sponsored Programs for their review.

7. Sponsored Programs will review the budget and notify the accounting tech of any questions or corrections.

8. If there are no corrections that need to be made, the accounting tech will send an email or voicemail to the PI(s) with instructions to sign the SP-1 in PASS. The lead PI must sign the SP-1 first in order to open the signature process up to all others. Once the PI signs the electronic SP-1 it will automatically be routed through the department, college and OSP for electronic signatures.

9. Once Sponsored Programs has reviewed and signed the original business section of the proposal, they will complete and provide the following to the PI;
• applicable assurances, representatives and certifications pages
• Sponsored Programs cover letter
• packaging and mailing instructions

If the submission is a paper copy:

10. PI picks up the signed face page & transmittal letter from Sponsored Programs and prepares the proposal for mailing.

If the proposal is to be submitted electronically through grants.gov:

11. The entire proposal package is transmitted to the accounting techs who will forward it to Sponsored Programs for uploading. (*Sponsored Programs requires at least 10 days prior to submission date.)

12. The proposal then moves through the system to be reviewed and hopefully awarded by the granting agency. Sponsored Programs will work directly with the PI with any additional questions or issues at this point.

*PASS - The Proposal Approval and Support System (PASS) is the location to enter general information regarding planned proposals. PASS provides proposal notification to Sponsored Programs and serves as the mechanism to obtain approval to submit to a Sponsor.

**SP-1 Sponsored Project Approval Form – The SP-1 is the internal document that the Office of Sponsored Programs requires be completed before your proposal can be submitted.


Mailing Address

Department of Clinical Sciences
College of Veterinary Medicine and Biomedical Sciences
Colorado State University
Fort Collins, CO 80523-1678

Phone: (970) 297-1274
FAX (970) 297-1275
Morna.Mynard@colostate.edu